UPGRADE OF FIRE PROTECTION NETWORKS AT 3 SITES

SENTSTOCK

UPGRADE OF FIRE 

PROTECTION NETWORKS 

AT 3 SITES (MBAO, PB AND PN) 

2023 –2024

The mission concerns the three SENSTOCK sites below:

  • The SENSTOCK MBAO FIRE PROTECTION system includes 2 FIRE PROTECTION tanks of 10,000 m3 and 3,000 m3, a pumping station and the FIRE PROTECTION distribution network in accordance with master plan MB-04-SENSTOCK-DEPOT MBAO-RESEAU FIRE PROTECTION-E and PID MB-14-SENSTOCK-DEPOT MBAO-PID-FIRE PROTECTION-A;
  • SENSTOCK's FIRE PROTECTION system for the PRODUIT BLANC depot includes 1 FIRE PROTECTION tank, a pumping station and the FIRE PROTECTION distribution network in accordance with master plan PB-30-RESEAU FIRE PROTECTION and PID PB-14B-SENSTOCK-DEPOT PRODUIT BLANC-PID FIRE PROTECTION;
  • SENSTOCK’s FIRE PROTECTION system for the BLACK PRODUCT depot includes offshore suction, pumping and the FIRE PROTECTION distribution network according to master plan 221437-02-SENSTOCK-PN-REFONTE FIRE PROTECTION-PID-PROJET-B.

With this mission, SENSTOCK wishes to verify the possibilities of modifications to be made to the existing networks following : 

  • Increase in equipment;
  • Pressure losses;
  • Necessary flow rates;
  • Maintaining the network pressurized to 12 bars.

It consists of :

  • Conducting an audit of existing networks by determining;
  • Integrate modifications to be made to existing networks according to the attached memo to improve our FIRE PROTECTION and meet POI recommendations.

Client: SENSTOCK



STUDY AND MONITORING OF THE NEW TANKER LINE